Dear Friends,
I’m thrilled to share with you the latest progress on the construction of the CVTI institute. Over the past two weeks, our team of 10 workers has been working diligently to bring this project to life. Here’s a snapshot of our recent accomplishments:
- We’ve completed tying up the rebar beams across both blocks.
- We’ve connected the partially built walls.
- We’ve partitioned the administration section into four offices.
Now that we’ve reached the wall plate level, we must install the veranda columns and tie up the veranda beams with the columns while other components dry.
I’m grateful to God for our progress so far and appreciate the hard work of our team. Thank you to JesusFedMe and our generous donors – your support means the world to us. May God bless you abundantly.